From Tepco website June 30, 2014
- ◯Breakdown of transferred assemblies by kind
Spent fuel1166 assemblies/1,331 assemblies
Unirradiated (New) fuel22 assemblies/ 202 assemblies - ◯Number of times of cask transportation:
54 times
as of June.30,2014
*The fuel removal work is stopped from July 1 to early
September of 2014 due to annual ceiling crane checkup